Project Details
S&B delivered FEL and EPC for a greenfield 182,000 bbl/day ethane export terminal capable of receiving VLECs (Very Large Ethane Carriers). The project included an 800,000 bbl refrigerated tank, demethanizer column, refrigeration facilities, boil-off gas (BOG) facilities, product transfer lines to the dock and associated utilities and offsites.
We delivered the project on schedule and within budget, despite significant impacts from the COVID-19 pandemic and multiple severe weather events.
This is one of only three major ethane export terminals in the US. S&B has played a leading role in all three terminals, including full EPC for two and EP for the third.