Progress Energy - Hines Energy Complex - Power Block 4

The team of S & B and Kiewit Power Engineers (KPE) provided engineering, procurement, and construction for the Power Block 4 (PB4) project. S & B and KPE executed this EPC combined cycle project located near Bartow, Florida as a joint venture entity.
 
This was a 582 megawatt combined cycle power plant utilizing a 2x1 dual fuel GE 7FA gas turbine with GE D11 steam turbine and triple pressure Nooter/Eriksen heat recovery steam generators (HRSGs). 

S & B was responsible for overall management of the project as well as purchasing and construction.
 
Detailed engineering, construction support, and start-up/ commissioning management were provided by Kiewit Power Engineers.